Quogue sits just updrift of Westhampton's groin field — a gentler shore than its famous neighbor, but a net-retreating one, with about 73% of its transects losing land. The village has spent two decades debating who should pay to hold it. Here's the record.

The record

What USGS and FEMA measured here.

Long-term rate
−0.16 m/yr
Reach mean, USGS DSAS long-term rate (≈ −0.52 ft/yr).
Worst transect
−0.37 m/yr
Fastest-eroding transect in the reach (≈ −1.2 ft/yr).
Shore eroding
73%
Share of transects in the reach losing land long-term.
FEMA zone
VE
Coastal high-hazard (wave action) at the oceanfront — FEMA NFHL.

Rates are the USGS National Assessment of Shoreline Change (Open-File Report 2010-1118/1119, Hapke et al.). Quogue is inside the same federal Fire-Island-to-Montauk-Point reach as Westhampton but updrift of the groins, so it hasn't been starved as severely — the erosion is real but milder. For the exact rate at a specific parcel, see the address certificate.

The questions people ask

Quogue beach erosion, straight.

Is Quogue losing its beach?

Yes, mostly — about 73% of USGS transects along Quogue erode long-term, averaging about −0.16 m/yr and reaching about −0.37 m/yr (−1.2 ft/yr) at the worst — gentler than Westhampton just downdrift, but still a net-retreating shore.

What is the Quogue shoreline-change rate?

The USGS long-term rate averages about −0.16 m/yr and reaches roughly −0.37 m/yr (about −1.2 ft/yr) at the fastest transect.

Did Quogue build an erosion-control tax district?

No — after years of nourishment proposals, the village board rejected a beach-erosion-control taxing district in 2019, and in 2020 the mayor pointed to joining the federal FIMP project as the most likely route to getting sand on the beach.

What FEMA flood zone is Quogue in?

The oceanfront is mapped Zone VE, the coastal high-hazard zone subject to breaking-wave action, in the FEMA National Flood Hazard Layer.

How it got this way

Two decades of deciding who pays.

Quogue's erosion is less dramatic than Westhampton's, and that has been its problem: not bad enough to force a federal rescue, bad enough that the beach keeps thinning while the village argues over who should fund the sand.

1997
Quogue adopts a Coastal Erosion Hazard Areas code (Chapter 80) and accepts a generic environmental review of beach-erosion options.
2010–2016
Dune Road homeowners press the village to nourish the ~2.7-mile beach; the village secures a NYS DEC tidal-wetlands permit in 2016 but shelves the project in 2017 as too expensive.
2019
The village board rejects a beach-erosion-control taxing district that would have assessed 44 oceanfront owners for a scaled-down eastern-beach plan.
2020 →
The mayor pivots to the federal FIMP project (fully federally funded) as the most likely path to sand; Quogue's formal status in FIMP is not confirmed in the public record as of this writing.

A local advocacy group reports the Quogue public-beach shoreline narrowed from about 1,000 ft to roughly 400 ft between 1976 and 2018 — an advocacy figure, not a federal measurement, but consistent with the net-eroding USGS trend above.